How to resume an interrupted O2O tasks for two days?

$
0
0
Hi,

Could someone advise what's the process to resume replication of a task that got interrupted for some reason and kept it on hold until two days?

What was attempted so far : 1. resume processing 2. Advanced Run Options - start processing changes from the day it ended.

This task is a two-steps redo log based run. One will read all the logs from source and store it in a file, second task will read logs from a file. This is Oracle-2-Oracle replication.

However, the task is throwing error as:

Stream component 'st_0_S' terminated
Stream component failed at subtask 0, component st_0_S
Error executing source loop
Endpoint is disconnected
Oracle CDC stopped

Can you please suggest how to resume the task or the best practice during the circumstances like this?

Thanks,
mk